How long does it take to get my development connected to the Chorus network?
The size of your development and the number of connections required will determine how long it takes to get your development connected to our network. Below is a guide of timeframes for a development with 5-200 lots.
Quote and contract: within one week from receiving your application
Design: one month from receiving your signed contract and payment
Build: between 30-90 days depending on complexity, availability of technicians, your timeframes and council permits